STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 INSTALLATION / OWNER’S MANUAL Improper installation, adjustment, alteration, service o
10 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 WARNING Improper installation, adjustment, alteration, service or maintenance can cau
11 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 6. MOUNTING CLEARANCES This heater must be mounted with at least the minimum clearanc
12 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 * RECOMMENDED MOUNTING HEIGHTS are typical to provide optimum comfort in general spac
13 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 System Configuration 1 Straight line 2 “U” tube with 2 x 90° elbow kits 3 “L” t
14 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 90° ELBOW KIT ASSEMBLY #1 Add the coupler to the 90° elbow over the swaged end
15 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 #6 After installation of the elbow assembly, fasten the corners of the reflector
16 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 #11/A Suspend with 3 chains in horizontal posi-tion and continue installing t
17 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 8. SUSPENDING THE SYSTEM - GENERAL Inadequate or improper suspension of the tube heat
18 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 5) Please NOTE that each hanger has a ‘flat’ side and a ‘cavity’ side – FIGURE 6 a)
19 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 FIGURE 8 REFLECTOR STABILIZER FIGURE 9 PLATE HANGER/ELBOW INSTALLATION see sect
2 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 NOTICE: This manual is current for this product. Occasional revision of the product C
20 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 8-A. SEISMIC RESTRAINT - LATERAL AND LONGITUDINAL In areas prone to earthquake, or a
21 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 9. BURNER AND TUBE INSTALLATION PRIOR TO PROCEEDING with the tube installation: Rea
22 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 7) NOTE: 175,000 & 200,000 Btuh Systems: Refer to Section 9.1, Fig 13 The
23 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 · Do not loosen or remove the fifth nut directly below the burner flange · Secure sus
24 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 TOOLS REQUIRED ¼” Drill Bit (supplied) Electric Drill SPECIAL COUPLER INSTALLATI
25 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 The focus shield reflector system can be adjusted to either side up to 45° from horiz
26 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 NOTE: Except for the vent end plate hanger, all hangers must be installed with the ca
27 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 11. FLUE VENTING Inadequate venting of a heater may result in asphyxiation, carbon
28 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 HORIZONTAL VENT THROUGH THE SIDEWALL: The flue vent system must slope downwards ap
29 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 Use the approved 4" (10 cm) (JA-0528-XX) or 6" (15 cm) (JA-0529-XX) hori
3 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 TABLE OF CONTENTS TOPIC ...PAGE INS
30 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 11A. Combined Length of Vent and Combustion Air Duct: The individual flue vent or
31 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 The air intake will not be located less than: Three feet above grade Twelve inc
32 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 13. GAS SUPPLY - HEATER EXPANSION - FLEXIBLE GAS CONNECTION The gas supply must be in
33 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 NOTE: Access to the manifold pressure test port is on the top of the valve. A 3/16&qu
34 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 The flue vent, and combustion air duct (if installed) must also be configured in suc
35 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 14. ELECTRICAL AND THERMOSTAT WIRING (WIRING DIAGRAMS PAGE 35 & 36) The heat
36 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 Each tube heater requires 120V, 60 HZ electrical power sized for 145VA. The heater
37 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 19. MULTIPLE TUBE HEATERS per THERMOSTAT Each tube heater requires 120V, 60 HZ ele
38 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 20 SEQUENCE OF OPERATION GASLITER 50N DIRECT SPARK IGNITION (DSI) The Gasliter 50N is
39 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 CHECK 120V SUPPLY TO RELAY SWITCH IF ELECTRICAL SUPPLY PROBLEM …. MAKE RE-QUIRE
4 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 APPLICATION This model is approved for indoor and outdoor installation. A gas-fired ra
40 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 MAIN BURNER LIGHTS SYSTEM RUNS UNTIL CALL FOR HEAT ENDS CALL FOR HEAT ENDS: SYSTEM S
41 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 22. SPARK IGNITION CIRCUIT The step-up transformer in the ignition control provides
42 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 24. START-UP / COMMISSIONING SHEET COMMISSION
43 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 TYPE OF GAS: NG LP DOES BUILDING HAVE A NEGATIVE CONDITION: YES NOIF THIS IS A HI
44 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 Manufactured and shipped in 10 ft lengths. Swaged tube has approximate 4 inch
45 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 FIGURE 22 HANGER SPACING / AIR INTAKE TO VENT LENGTH FIGURE 8 HANGER / REFLECTO
46 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 26A. BURNER & TUBE KIT ASSEMBLY CHART MODELS STW-JZ / IW Models STW-JZ /IW have
47 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 26B. BURNER & TUBE KIT ASSEMBLY CHART MODELS STW-JZ2 / IW2 Models STW-JZ2 /IW2
48 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 27.GAS CONVERSION OF BURNER - MODELS STW-JZ / IW Burners for the STW-JZ / IW Models
49 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 MODEL TURBULATOR LENGTH (IF REQUIRED) STW-JZ / IW 200-70/60/50 10’ (3 m) STW-JZ / I
5 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 Heater Expansion It is a normal condition that during heat-up and cool-down a tube he
50 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 ORIFICE CHART - ALTITUDE CONVERSION ~ SEE NOTES ON PREVIOUS PAGE ~ 29. HIGH ALTITUD
51 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 30. OPTIONAL ACCESSORIES Flue Vent Terminal 4” wall horizontal 6” wall horizontal J
52 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 90 degree Elbow Kit* Aluminized Steel JS-0508-JZ Stainless Steel JS-0508-
53 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 #2 Lion Chain (115 lb work load) - 200 ft roll ‘S’ Hooks - 1 7/8” - package of 25
54 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 31. REPLACEMENT PARTS STW-JZ (-JZ2) / IW (-2) Burner Model STW-JZ2 (stainless steel t
55 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 SEE EXPLODED V IEW OF BURNER ON PREVIOUS PAGE# PART DESCRIPTION PART # PART DESCRIPTI
56 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 STW-JZ (-JZ2) / IW (-2) TUBE SYSTEM PARTS # PART DESCRIPTION PART # PART DESCRIPTION
57 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 LIMITED WARRANTY CERTIFICATE FOR GAS-FIRED INFRA-RED LOW INTENSITY TUBE HEATERS: STW-
6 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 Clearance to combustibles Location of flammable or explosive objects, liquids or vapo
7 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 TABLE 1 MINIMUM CLEARANCES TO COMBUSTIBLES* FIGURE 1 MINIMUM CLEARANCES TO COMBUSTIB
8 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 VENT END CLEARANCE: Clearances from the vent pipe are determined by local or national
9 STW-JZ / IW I&O Manual IM101229 RL: 12A- BA RD: DEC 2010 2. INSTALLATION IN COMMERCIAL AIRCRAFT HANGARS Low intensity radiant tube heaters are